Construction Update July 2025
The Culcairn Solar Farm has been energised and has started delivering its first electrons into the grid! We are thankful to the support of all the teams involved to reach this milestone, while prioritising work, health, and safety on our site.
Some key updates and achievements include:
- 100% of piles (98,000 total) have been installed successfully in the ground across the project site
- installation of the PV tracking structure is 100% complete
- 100% of the inverter stations have been installed
- 99% of PV panels have been installed onsite
- 100% of underground cables have been installed across the site
- The substation works have been completed and our two High Voltage Siemens transformers were energised in June!
- Culcairn Solar Farm was officially registered with AEMO on 10 June 2025, a major milestone.
- We started supplying our first electrons from this asset into NSW’s electricity network and are excited to progress the commissioning of Neoen’s second largest solar farm in Australia!
Should you have any queries or concerns in relation to the works, please don’t hesitate to contact us on 1800 966 122 or email us through the contact page.